Road surfacing in Kingsgrove

The following is from ACS, who are the main infrastructure contractor on the Kingsgrove development.

It was sent through the Kingsgrove Community team, aka Brighton STM Developments as master developer. If you want to receive these type of updates directly via e-mail then please subscribe here. Any emphasis is mine.


We are about to start the final phase of the Elder Way finishing works, which involve the surfacing of the footpaths, cycle lanes and main carriageway. Planing work began earlier this week.

Due to the quantity of material we can lay in one day, we will need to close Elder Way for four days total in November (17th-20th), with access on and off drives being restricted on the 17th & 18th (as per below drawing).

Frontages will be accessible on 19th & 20th, but the road closure will remain whilst cycleways are resurfaced. Footpaths will remain open for pedestrian access during the closure.

The current timeline for surfacing is as follows:

  • 17th November – Bus Gate to Cowslip Road surfacing (left side AM / right side PM)
  • 18th November – Cowslip Road to The Hub surfacing (left side AM / right side PM)
  • 19th & 20th November – Cycle Lane surfacing

This does mean vehicle access will be unavailable to some Elder Way residents during the dates and times above. Affected homes will have received a letter including the map below.


On a related note, whilst at the Crabhill Development Forum last week, I discovered that the corresponding works for other roads are delayed, because

Final agreement of the highway design with OCC Highways relating to Cherry Croft, Primrose Avenue & Rutherford Road remains outstanding.

Works on these roads will therefore be delayed until an agreement is reached, and Road Safety Audits are carried out.

Now, the following is pure speculation on my part but I think that this lack of final agreement might be because of the traffic calming measures that are, or in the case of Rutherford Road, aren’t, in the original planning documentation.

  • Cherry Croft was planned to have traffic calming chicanes, in similar way to Primrose Avenue.
  • Primrose Avenue’s traffic calming measure might have to be removed due to the construction of any development on Fullers Field.
  • Rutherford Road has been the subject of discussion relating to the need for traffic calming measures outside the school.